Vertical Integration Facility Door Replacement

On October 24, 2005 Hurricane Wilma blew through the LC-41 pad and precipitated the catastrophic failure of a major portion of the 40 foot wide by 280 foot tall folding fabric door (Megadoor) on the vertical integration facility (VIF) which houses the launch vehicle that was inside at that time. IMEG engineers were on-site the