Facility Renovation & Addition

Goshen Health Systems had a goal to be the first to market with the latest and most refined types of cancer care available. Therefore, this project had an extremely challenging design and construction schedule. The project duration from initial design kick-off meetings to the first day of seeing patients was 10 months. IMEG, specifically requested